Client: Thai Oil Public Co., Ltd

Project: Thai Oil Clean Fuel

  • Site management and supervision for load-in, loadout and transshipment activities of various modules and equipment from 15te up to 2069te in 3 area, consists of Sattahip Commercial Port, Laem Chabang Port and Kerry Siam Sea Port. Totally 63 shipments in 2.5 years were delivered via barge to Thai Oil Clean Fuel Project.
  • Supervise sub-contractors for the document/drawing preparation to apply the permits from local authority until present to those parties as the client representative.
  • Create stowage yard and management to utilize whole area for more efficiency and suit the project requirements.
  • Present to the local and other authorities according to Project requirements

Client: GE

Project: 45 MW Rom Kloa Wind Farm Project

  • 13 Wind Turbine of v136- 3.45 at HH 162m. inland transportation and installation at Mukdahan, Thailand.
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Advise the various transportation of wind turbine components to site
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client

Client: GE

Project: 450 MW T5 Wind Power Project

  • 90 Wind Turbine of GE3.43-137 at HH157m. inland transportation and installation at Nakorn Ratsima and Chaiyaphum, Thailand.
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Advise the various transportation of wind turbine components to site
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client

Client: Siemens Co., Ltd.

Project: Phuket 3 Power Plant

  • Transport 2 of 80te transformer from LCB Port to Phuket 3 Power Plant, Thailand
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client

Client: Hansa Meyer Global Transport Co., Ltd.

Project: Xayaburi Hydro Power Plant

  • Transport of various Hydro Power Plant Equipment 50 te up to 170te transformer from LCB Port, Thailand to Xayaburi, Laos
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Advise the various transportation of Hydro Power Plant Equipment to site
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client
  • Transformer installation

Client: FLS

Project: ALBA POWER STATION Project

  • Advise and approval Procedures, Method Statements and Safety Analysis.
  • Transport of various component and modules 4 shipment from Sattahip Navy Port to under the hook at LCB Port, Thailand

Client: GE

Project: 60MW Khao Kor Wind Power Project

  • 24 Wind Turbine of GE–2.5-120 at HH110m. inland transportation and installation at Khao Kor Phetchabun, Thailand.
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Advise the various transportation of wind turbine components to site
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client

Client: GE

Project: 75 MW Watabak Wind Farm Project

  • 30 Wind Turbine of GE2.5-120 at HH120m. inland transportation and installation at Watabak Chaiyaphum, Thailand.
  • Project organized at office base
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Advise the various transportation of wind turbine components to site
  • Apply the permit of Department of Highway and Local Authority
  • Company Representative present the project to all parties/Authority on behalf of client

Client: CUEL Ltd., Co.

Project: Ichthys Onshore LNG Facilities Project

  • 151 LNG Modules Weighing and Loadout varies weight from 100-2,000te by SPMT at CUEL, Thailand.
  • Advise and approval for Procedures, Method Statements and Safety Analysis.
  • Project organized at site base
  • Project cost control
  • Project schedule control

Client: Clough Thailand

Project: MANORA, Thailand

Load-outs at Sattahip Navy Port

  • Weighing, load-out by SPMT and ballasting Topsides 2740te and Jacket 518te
  • Formulate Method Statements and Safety Analysis.
  • Organize and project management

Client: Schenker Australia Pty Ltd

Project: GORGON-BARROW ISLAND LNG PLANT

  • Transport of 5 CBI tanks from Sattahip to LCB Port, Thailand
  • Formulated Method Statement
  • Project co-coordinator that supervised the operational crews for the conventional trailers

 Client: THAI NIPPON STEEL AND SUMIKIN ENGINEERING & CONSTRUCTION CORP., LTD. 

Project: PTTEP Bundle Phases, CPOC, C-HESS, MACEDON,

SALAMANDER

  • Formulate procedures, Method Statements (SPMT’s transportation and Load-out) and Safety Analysis.
  • Organize and project management

Client: Best Tech and Engineering Co., Ltd

Project: SOLOMON

  • Formulate procedures, Method Statements and Safety Analysis.
  • Module weighing

Client: Eurotech Engineering International Co., Ltd.

Project: Gorgon

  • Formulate procedures, Method Statements and Safety Analysis.
  • Transport of various pipe rack modules to under the hook, then load onto the barge to Barrow Island.

Client: Experteam Co., Ltd

Project: FUNAN Stabilizer Column and E&I Room

  • Formulate procedures, Method Statements load-out at the Sattahip Naval Port, Thailand and Safety Analysis.
  • Module weighing

Client: Saipem Leighton Consortium, (AMC) Western Australia

Project: GORGON-BARROW ISLAND LNG PLANT

  • Formulate procedures, Method Statements (SPMT’s transportation, Load-ins and Load-out) and Safety Analysis.
  • Formulate Ballasting Calculation

Client: Aibel

Project: TUPI Module (FPSO):

  • Module weighing and load-out ballasting at the Port of LCB-C0, Thailand
  • Formulate produced Ballast Calculations, Procedures, Method Statements and Safety Analysis.

Client: Clough Thailand

Project: Songkhla Field, Thailand

Load-outs at Sattahip Navy Port

  • Weighing, load-out, and ballasting for 2 No Topsides and 2 No Jackets
  • Formulate procedures, Method Statements and Safety Analysis.

Client: DB Schenker

Project: Sepon Copper Mine                             

  • Transport of transformer from Thailand to Sepon Copper Mine, Laos
  • Formulated Method Statement
  • Project co-coordinator that supervised the operation crew for the conventional trailer maneuver

Client: Sahatum

Project: Nam Lik Power Plant

  • Transport of transformer from Thailand to Nam Lik Power Plant, Laos
  • Formulate Method Statement
  • Project co-coordinator that supervised the operational crew for the conventional trailer maneuver

Client: BJC and Logem

Project: BJC Module

  • Module weighing.

Client: Sino-Thai and Foster Wheeler

Project: PLUTO LNG

  • Module weighing.

Client: Qtec and Foster Wheeler

Project: PLUTO LNG

  • Module weighing and load-out ballasting at the Port of Sattahip Navy, Thailand
  • Formulate procedures, Method Statements and Safety Analysis.

Client: PTSC and Premier Oil

Project: Chim Sao and Topaz

  • Loadout and ballasting for Chim Soa and Topaz Topsides at PTSC Port Vung Tao, Vietnam

Client: Unimit

Project: Esso Sriracha Clean Fuel Project

  • Transport of various processes column with weight 90-130te from Unimit Shop to project site.
  • Formulate Method Statement
  • Project co-coordinator that supervise the operation crew for the conventional trailer maneuver

Client: Foster Wheeler

Project: Esso Sriracha Clean Fuel Project

  • Transport of various processes column and module with dressing area to lay down area and lay down area to under hook.
  • Formulate Method Statement
  • Project Site co-coordinator that supervise the operation crew for the SPT and SPMT maneuver

Client: Foster Wheeler

Project: TPO Dow Project

  • Transport of various processes column with weight from 50te-700te from Mapthaphut Port to lay down area and lay down area to under hook
  • Project Site co-coordinator that supervised the operational crew for the SPT maneuver

Client: Pt Gunanusa Utama Fabricator

Project: Oil and Natural Gas

  • 3 No module weighing (TGCM, PGCM and Building module) at Gunanusa Yard, Indonesia  

Client: Brooke Dock Yard & ENG Works Corpn.

Project: Belum and Pemains

  • Penamis jacket weighing at Kuching, Malaysia

Client: Unimit

Project: SPRC Clean Fuel Project

  • Transport of various processes column with weight from 53-115te from factory to project site
  • Formulated Method Statement
  • Project co-coordinator that supervise the operation crew for the conventional trailer maneuver

Provided engineering support for the following projects:

PLOCPP2 Production module (Oil Platform): 9,458te.                        

PLOCPP2 Utilities module (Oil Platform): 2,200te            

           

Unocal Phase 28/1(Gas Platform): 1,272te

Unocal Phase 28/2(Gas Platform): 1,360te

Unocal Phase 28/3(Gas Platform): 1,316te

Unocal Phase 28/4(Oil Platform): 1,356te

Unocal Phase 28/5(Gas Platform):1,291te           

Unocal Phase 28/6(Oil Platform):1,355te           

Unocal Phase 28/7(Gas Platform):1,280te           

 

M15 Chevron wellhead platform stage3: 1,536te

M16 Chevron wellhead platform stage3: 1,536te

M17 Chevron wellhead platform stage3: 1,536te

M18 Chevron wellhead platform stage3: 1,536te         

M19 Chevron wellhead platform stage3: 1,536te

 

Unocal Phase 29/1(Gas Platform):1,350te           

Unocal Phase 29/2(Gas Platform): 1,350te

Unocal Phase 29/3(Gas Platform): 1,350te

Unocal Phase 29/4(Gas/CO2 Platform): 1,350te

Unocal Phase 29/5(Gas Platform): 1,350te

 

Unocal Phase 29/6(Oil Platform): 1,350te

Unocal Phase 29/7(Oil Platform): 1,350te

 

Erawan Mercury Removal Platform (PTTEP): 2,382te

 

CTEP Phase 30/1(Gas Platform): 1,426te

CTEP Phase 30/2(Gas Platform): 1,363te

CTEP Phase 30/3(Oil Platform): 1,496te

CTEP Phase 30/4(Oil Platform): 1,436te

 

PEARL Jasmine B (Oil Platform): 1,932te

PEARL Jasmine C (Oil Platform): 2,066te

 

M20 Chevron wellhead platform stage3B: 1,776te

M21 Chevron wellhead platform stage3B: 1,650te

 

M22 Chevron wellhead platform stage3B: 1,776te

M23 Chevron wellhead platform stage3B: 1,738te

 

BGEP CPP Jacket: 949te

BGEP MTA Jacket: 435te

BGEP Flare tower: 173te           

BGEP CPP Bridge: 360te

 

Kencana BMA Jacket: 975te

Kencana SYA Jacket: 905te

Kencana BLA Jacket: 874te

Kencana CKR Module: 1,181te

 

CTEP Phase 31/1(Gas Platform): 1,350te

CTEP Phase 31/2(Gas Platform): 1,350te

CTEP Phase 31/3(Gas Platform): 1,350te

CTEP Phase 31/4(Gas Platform): 1,350te

 

CTEP Phase 32/1(Oil Platform): 1,350te

CTEP Phase 32/2(Gas Platform): 1,350te

CTEP Phase 32/3(Oil Platform): 1,350te

CTEP Phase 32/4(Gas Platform): 1,350te

CTEP Phase 32/5(Oil Platform): 1,350te

CTEP Phase 32/6(Gas Platform): 1,350te

CTEP Phase 32/7(Hub Platform): 1,350te

 

M24 Chevron wellhead platform stage4: 1638te 

M25 Chevron wellhead platform stage4: 1274te 

M26 Chevron wellhead platform stage4: 1268te

M27 Chevron wellhead platform stage4: 1268te 

M28 Chevron wellhead platform stage4: 1268te 

 

PEARL Jasmine B2: 1360te

PEARL Jasmine D: 1549te 

PEARL Jasmine Ban Yen A: 1555te             

 

CTEP Phase 33/1(Gas Platform): 905te   

CTEP Phase 33/2(Gas Platform): 958te   

CTEP Phase 33/3(Gas Platform): 998te   

CTEP Phase 33/4(Hub Platform): 1098te 

CTEP Phase 34/1: 1,585te           

CTEP Phase 34/2: 1,585te

CTEP Phase 34/3: 1,566te           

CTEP Phase 34/4: 1,566te           

CTEP Phase 34/5: 1,585te

 

CPOC MLQJ Jacket: 1,905te

 

BG Hydra – SWP: 2,333te

BG Hydra – PK: 2,383te           

 

HOEC: 3,899te

 

Suvarnabhumi International Airport (Super Truss of Main Terminal Bldg.): 7,000te

 

Roppongi Tower / Japan: 9,500te

 

North east tower / Hongkong: 12,000te

 

Maizuru power plant/ Japan: 1,800te

 

Bang Bo power plant / Thailand: 2,000te.

 

Industrial Ring Road Project (Suspension Bridge)/Thailand: 6800te.