Client: Thai Oil Public Co., Ltd
Project: Thai Oil Clean Fuel
- Site management and supervision for load-in, loadout and transshipment activities of various modules and equipment from 15te up to 2069te in 3 area, consists of Sattahip Commercial Port, Laem Chabang Port and Kerry Siam Sea Port. Totally 63 shipments in 2.5 years were delivered via barge to Thai Oil Clean Fuel Project.
- Supervise sub-contractors for the document/drawing preparation to apply the permits from local authority until present to those parties as the client representative.
- Create stowage yard and management to utilize whole area for more efficiency and suit the project requirements.
- Present to the local and other authorities according to Project requirements
Client: GE
Project: 45 MW Rom Kloa Wind Farm Project
- 13 Wind Turbine of v136- 3.45 at HH 162m. inland transportation and installation at Mukdahan, Thailand.
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Advise the various transportation of wind turbine components to site
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
Client: GE
Project: 450 MW T5 Wind Power Project
- 90 Wind Turbine of GE3.43-137 at HH157m. inland transportation and installation at Nakorn Ratsima and Chaiyaphum, Thailand.
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Advise the various transportation of wind turbine components to site
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
Client: Siemens Co., Ltd.
Project: Phuket 3 Power Plant
- Transport 2 of 80te transformer from LCB Port to Phuket 3 Power Plant, Thailand
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
Client: Hansa Meyer Global Transport Co., Ltd.
Project: Xayaburi Hydro Power Plant
- Transport of various Hydro Power Plant Equipment 50 te up to 170te transformer from LCB Port, Thailand to Xayaburi, Laos
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Advise the various transportation of Hydro Power Plant Equipment to site
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
- Transformer installation
Client: FLS
Project: ALBA POWER STATION Project
- Advise and approval Procedures, Method Statements and Safety Analysis.
- Transport of various component and modules 4 shipment from Sattahip Navy Port to under the hook at LCB Port, Thailand
Client: GE
Project: 60MW Khao Kor Wind Power Project
- 24 Wind Turbine of GE–2.5-120 at HH110m. inland transportation and installation at Khao Kor Phetchabun, Thailand.
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Advise the various transportation of wind turbine components to site
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
Client: GE
Project: 75 MW Watabak Wind Farm Project
- 30 Wind Turbine of GE2.5-120 at HH120m. inland transportation and installation at Watabak Chaiyaphum, Thailand.
- Project organized at office base
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Advise the various transportation of wind turbine components to site
- Apply the permit of Department of Highway and Local Authority
- Company Representative present the project to all parties/Authority on behalf of client
Client: CUEL Ltd., Co.
Project: Ichthys Onshore LNG Facilities Project
- 151 LNG Modules Weighing and Loadout varies weight from 100-2,000te by SPMT at CUEL, Thailand.
- Advise and approval for Procedures, Method Statements and Safety Analysis.
- Project organized at site base
- Project cost control
- Project schedule control
Client: Clough Thailand
Project: MANORA, Thailand
Load-outs at Sattahip Navy Port
- Weighing, load-out by SPMT and ballasting Topsides 2740te and Jacket 518te
- Formulate Method Statements and Safety Analysis.
- Organize and project management
Client: Schenker Australia Pty Ltd
Project: GORGON-BARROW ISLAND LNG PLANT
- Transport of 5 CBI tanks from Sattahip to LCB Port, Thailand
- Formulated Method Statement
- Project co-coordinator that supervised the operational crews for the conventional trailers
Client: THAI NIPPON STEEL AND SUMIKIN ENGINEERING & CONSTRUCTION CORP., LTD.
Project: PTTEP Bundle Phases, CPOC, C-HESS, MACEDON,
SALAMANDER
- Formulate procedures, Method Statements (SPMT’s transportation and Load-out) and Safety Analysis.
- Organize and project management
Client: Best Tech and Engineering Co., Ltd
Project: SOLOMON
- Formulate procedures, Method Statements and Safety Analysis.
- Module weighing
Client: Eurotech Engineering International Co., Ltd.
Project: Gorgon
- Formulate procedures, Method Statements and Safety Analysis.
- Transport of various pipe rack modules to under the hook, then load onto the barge to Barrow Island.
Client: Experteam Co., Ltd
Project: FUNAN Stabilizer Column and E&I Room
- Formulate procedures, Method Statements load-out at the Sattahip Naval Port, Thailand and Safety Analysis.
- Module weighing
Client: Saipem Leighton Consortium, (AMC) Western Australia
Project: GORGON-BARROW ISLAND LNG PLANT
- Formulate procedures, Method Statements (SPMT’s transportation, Load-ins and Load-out) and Safety Analysis.
- Formulate Ballasting Calculation
Client: Aibel
Project: TUPI Module (FPSO):
- Module weighing and load-out ballasting at the Port of LCB-C0, Thailand
- Formulate produced Ballast Calculations, Procedures, Method Statements and Safety Analysis.
Client: Clough Thailand
Project: Songkhla Field, Thailand
Load-outs at Sattahip Navy Port
- Weighing, load-out, and ballasting for 2 No Topsides and 2 No Jackets
- Formulate procedures, Method Statements and Safety Analysis.
Client: DB Schenker
Project: Sepon Copper Mine
- Transport of transformer from Thailand to Sepon Copper Mine, Laos
- Formulated Method Statement
- Project co-coordinator that supervised the operation crew for the conventional trailer maneuver
Client: Sahatum
Project: Nam Lik Power Plant
- Transport of transformer from Thailand to Nam Lik Power Plant, Laos
- Formulate Method Statement
- Project co-coordinator that supervised the operational crew for the conventional trailer maneuver
Client: BJC and Logem
Project: BJC Module
- Module weighing.
Client: Sino-Thai and Foster Wheeler
Project: PLUTO LNG
- Module weighing.
Client: Qtec and Foster Wheeler
Project: PLUTO LNG
- Module weighing and load-out ballasting at the Port of Sattahip Navy, Thailand
- Formulate procedures, Method Statements and Safety Analysis.
Client: PTSC and Premier Oil
Project: Chim Sao and Topaz
- Loadout and ballasting for Chim Soa and Topaz Topsides at PTSC Port Vung Tao, Vietnam
Client: Unimit
Project: Esso Sriracha Clean Fuel Project
- Transport of various processes column with weight 90-130te from Unimit Shop to project site.
- Formulate Method Statement
- Project co-coordinator that supervise the operation crew for the conventional trailer maneuver
Client: Foster Wheeler
Project: Esso Sriracha Clean Fuel Project
- Transport of various processes column and module with dressing area to lay down area and lay down area to under hook.
- Formulate Method Statement
- Project Site co-coordinator that supervise the operation crew for the SPT and SPMT maneuver
Client: Foster Wheeler
Project: TPO Dow Project
- Transport of various processes column with weight from 50te-700te from Mapthaphut Port to lay down area and lay down area to under hook
- Project Site co-coordinator that supervised the operational crew for the SPT maneuver
Client: Pt Gunanusa Utama Fabricator
Project: Oil and Natural Gas
- 3 No module weighing (TGCM, PGCM and Building module) at Gunanusa Yard, Indonesia
Client: Brooke Dock Yard & ENG Works Corpn.
Project: Belum and Pemains
- Penamis jacket weighing at Kuching, Malaysia
Client: Unimit
Project: SPRC Clean Fuel Project
- Transport of various processes column with weight from 53-115te from factory to project site
- Formulated Method Statement
- Project co-coordinator that supervise the operation crew for the conventional trailer maneuver
Provided engineering support for the following projects:
PLOCPP2 Production module (Oil Platform): 9,458te.
PLOCPP2 Utilities module (Oil Platform): 2,200te
Unocal Phase 28/1(Gas Platform): 1,272te
Unocal Phase 28/2(Gas Platform): 1,360te
Unocal Phase 28/3(Gas Platform): 1,316te
Unocal Phase 28/4(Oil Platform): 1,356te
Unocal Phase 28/5(Gas Platform):1,291te
Unocal Phase 28/6(Oil Platform):1,355te
Unocal Phase 28/7(Gas Platform):1,280te
M15 Chevron wellhead platform stage3: 1,536te
M16 Chevron wellhead platform stage3: 1,536te
M17 Chevron wellhead platform stage3: 1,536te
M18 Chevron wellhead platform stage3: 1,536te
M19 Chevron wellhead platform stage3: 1,536te
Unocal Phase 29/1(Gas Platform):1,350te
Unocal Phase 29/2(Gas Platform): 1,350te
Unocal Phase 29/3(Gas Platform): 1,350te
Unocal Phase 29/4(Gas/CO2 Platform): 1,350te
Unocal Phase 29/5(Gas Platform): 1,350te
Unocal Phase 29/6(Oil Platform): 1,350te
Unocal Phase 29/7(Oil Platform): 1,350te
Erawan Mercury Removal Platform (PTTEP): 2,382te
CTEP Phase 30/1(Gas Platform): 1,426te
CTEP Phase 30/2(Gas Platform): 1,363te
CTEP Phase 30/3(Oil Platform): 1,496te
CTEP Phase 30/4(Oil Platform): 1,436te
PEARL Jasmine B (Oil Platform): 1,932te
PEARL Jasmine C (Oil Platform): 2,066te
M20 Chevron wellhead platform stage3B: 1,776te
M21 Chevron wellhead platform stage3B: 1,650te
M22 Chevron wellhead platform stage3B: 1,776te
M23 Chevron wellhead platform stage3B: 1,738te
BGEP CPP Jacket: 949te
BGEP MTA Jacket: 435te
BGEP Flare tower: 173te
BGEP CPP Bridge: 360te
Kencana BMA Jacket: 975te
Kencana SYA Jacket: 905te
Kencana BLA Jacket: 874te
Kencana CKR Module: 1,181te
CTEP Phase 31/1(Gas Platform): 1,350te
CTEP Phase 31/2(Gas Platform): 1,350te
CTEP Phase 31/3(Gas Platform): 1,350te
CTEP Phase 31/4(Gas Platform): 1,350te
CTEP Phase 32/1(Oil Platform): 1,350te
CTEP Phase 32/2(Gas Platform): 1,350te
CTEP Phase 32/3(Oil Platform): 1,350te
CTEP Phase 32/4(Gas Platform): 1,350te
CTEP Phase 32/5(Oil Platform): 1,350te
CTEP Phase 32/6(Gas Platform): 1,350te
CTEP Phase 32/7(Hub Platform): 1,350te
M24 Chevron wellhead platform stage4: 1638te
M25 Chevron wellhead platform stage4: 1274te
M26 Chevron wellhead platform stage4: 1268te
M27 Chevron wellhead platform stage4: 1268te
M28 Chevron wellhead platform stage4: 1268te
PEARL Jasmine B2: 1360te
PEARL Jasmine D: 1549te
PEARL Jasmine Ban Yen A: 1555te
CTEP Phase 33/1(Gas Platform): 905te
CTEP Phase 33/2(Gas Platform): 958te
CTEP Phase 33/3(Gas Platform): 998te
CTEP Phase 33/4(Hub Platform): 1098te
CTEP Phase 34/1: 1,585te
CTEP Phase 34/2: 1,585te
CTEP Phase 34/3: 1,566te
CTEP Phase 34/4: 1,566te
CTEP Phase 34/5: 1,585te
CPOC MLQJ Jacket: 1,905te
BG Hydra – SWP: 2,333te
BG Hydra – PK: 2,383te
HOEC: 3,899te
Suvarnabhumi International Airport (Super Truss of Main Terminal Bldg.): 7,000te
Roppongi Tower / Japan: 9,500te
North east tower / Hongkong: 12,000te
Maizuru power plant/ Japan: 1,800te
Bang Bo power plant / Thailand: 2,000te.
Industrial Ring Road Project (Suspension Bridge)/Thailand: 6800te.